mardi 22 novembre 2016

Commissioning Flamanville EPR in 2018? Really? Yes, answers EDF

From "Les Échos", November 15th, written by Véronique Le Billon


The French power operator grants that Flamanville reactor tank will abide by regulatory standards and that the EPR shall be commissioned in late 2018. Moreover, the company forecasts a €5 billion cost-reduction for its own reactor models.
On site, the visitor smells warm iron of welded metal, sees scaffolds still congesting the machine room and meets some 4,300 staff of EDF and contractors working in the maze of hallways and stairs, but now, the site really looks like a nuclear power plant. EDF expresses its confidence to be able to commission the reactor in late 2018, during a visit on Flamanville construction site on Wednesday, following its CEO’s pledge made in September 2015, whereas the project has recorded several overcosts and delays.

The program is challenging but realistic.


« We consider that the project is back on track. The program is quite challenging but realistic and we will stick to the next scheduled steps », said Xavier Ursat, who is the group executive director in charge of new nuclear projects. The first assembly trials of the reactor are scheduled before the end of 2017 first quarter, confirmed EDF. The last assemblies and completion shall last until the end of next year, outlined Bertrand Michoud, who has just been appointed manager of the « FA3 » project. Launched in 2007, the reactor should have been first commissioned in 2012.

« Fit for service »

The public power operator displays the same confidence about the compliance of the EPR tank, though an excessive carbon concentration, detected in the lid and in the bottom of the tank in late 2014. EDF and Areva have launched trials on three representative parts of the tank, which shall last in a ten days’ time. « We have already got nearly 90% of the results, and all these figures comply with the standards requested by the Nuclear Safety Authority (ASN, French acronym). And the 10% left are made in areas where the carbon concentration is much smaller», said Laurent Thieffry, project manager of Flamanville 3. « Thus, we are very confident in the fact that the tank shall be deemed fit for service ».
Following the « defects » found in the production files on the Areva plant of Le Creusot (Saône-et-Loire), EDF is waiting also the results of an audit made by Areva on 93 parts ; this audit shall be concluded in late December. As for Fessenheim 2, the NSA has already requested controls on the resistance of a steam generator, whose data production have been forged. The investigation will last six months, but, on that point also, EDF shows confidence.
Finally, the power operator is waiting the three-year extension of the decree of authorisation to create the nuclear facility, which shall normally expiry next spring.

Taishan site in China


Last week, EDF CEO, Jean-Bernard Levy, visited Taishan site, in China, where EDF shall be  joint operator of two EPRs together with CGN, its Chinese partner (with a 30% stake for EDF). Taishan 1 shall be the first EPR in service in the world, unless a particular event happens. The trials in conditions of pressure and temperature (known as « warm trials ») have just begun. Charging fuel is expected before the end of 2017 first semester, before the operating commissioning (functioning at full power), some months later. Taishan 2 shall be commissioned six months to one year later.
Wednesday, beyond the Flamanville 3 project agenda, EDF confirmed also that the revised budget won’t change, namely « at maximum €10,5 billion ». At the beginning of the project, the budget amounted to €3,3 billion.

READ ALSO

A new variant of EPR

EDF is working on the design of an optimized version of the EPR, which may result in a cost reduction of €5 billion of its EPR NM (EPR new model), compared with the cost of Flamanville EPR for the same power (1,650MWh). Among the different possible options, which are not yet decided according to Xavier Ursat, there are : the choice of a simple containment building around the reactor building, and three instead of four « safety trains », which are safety devices allowing the reactor safety by redundancy. Discussions are already scheduled with the NSA.
In operating conditions, 420 staff will work on Flamanville 3 beside the two other reactors. The operating room (control-command) has already been transferred to the operator.


FINNISH EPR: AREVA’S PARTNER WORRIES

Olkiluoto site in Finland

In Olkiluoto, far from Flamanville and EDF’ confidence, TVO, the Finnish partner, shows deep worries about the end of the EPR construction, built with Areva. The project started in 2005, but, the years coming by, it has become an industrial quagmire for the French group, torn apart between delays and overcosts.
TVO worries about the consequences of the French nuclear sector restructuration, according which EDF shall buy Areva’s reactor division (known as Areva NP), but with the exception of OL3, the Finnish EPR project. « TVO is really aware that the future Areva SA won’t have the necessary financial resources to conclude the project », hammered a spokeman on Wednesday. The (Finnish) group « considers that separating the ownership of the agreement from the necessary resources to finish and to commission the OL3 EPR is not a fair behaviour from the part of a nuclear technologies manufacturer ». 

mardi 4 août 2015

EPR: the Finnish operator claims now €2,6 billion to the French consortium

Energygeopole blog provides latest energy, nukes, oil and gas, renewables news from France, acting as a global actor through its role in the European Union, and through its majors in the energy sector. Stay connected with the latest trends and analysis through translations of relevant articles from the French press into English on a weekly basis.

TVO and Areva-Siemens


Olkiluoto EPR


"Les Échos" on August, 3rd.


Reactor commissioning is scheduled for late 2018 - AFP PHOTO/AIRA VEHASKARI


First, the operator claimed  a €2,3 billion compensation. On its part, the manufacturing consortium has kept its own request for damage at €3,4 billion.


TVO and Areva-Siemens carry on blaming each other for dysfunctions. The Finnish utility, which is the future operator of an EPR reactor build by the consortium, stated that the company decided to increase its claim for compensation from €2,3 billion to €2,6 billion to Areva-Siemens, because of the delays in implementing the construction.
The Arbitration Court of the International Chamber of Commerce (ICC) is currently examining this case, in which each party blames the other one. 
Among TVO's shareholders, there are Finnish paper manufacturers UPM and Stora Enso, and the Fortum Group, specialized in services to communities. 
TVO also stated that the consortium has kept its own claim at €3,4 billion.


Waiting for a year-long decision


"The case focuses on events, which took place during the construction period until late 2011 (...). The claimed amount includes defaults interest (...) and late payments charged to TVO, amounting to some €1,4 billion, together with some €140 millions due to an alleged profit loss", wrote TVO in a statement.  
Whereas reactor manufacturers blame TVO for administrative impediments that make their work slower and more difficult.
Risto Siilos, TVO's Deputy General Director, repeated that the ICC may issue its arbitration only after several years. In April, some sources close to the French nuclear group told Reuters that a part decision could be made in the end of the year.


"Despite the arbitration process, the project carries on"


According to the latest information, the reactor commissioning has been scheduled for December 2018, which means a ten-year delay, as the reactor should have been commissioned in 2009. Considering this delay, TVO has recently given up the construction of a fourth reactor on its site.
'Despite the arbitration process, the project carries on", highlighted Risto Siilos.
Thursday, Areva officially transferred the main part of its reactors division to EDF, which has made sure to take no part at all in the financial risks relating to the Finnish project. "We would warmly welcome any initiative of the French nuclear industry in order to help Areva to carry out the Olkiluoto project", said Risto Siilos, referring to this transfer to EDF.

Reading further...
http://www.lesechos.fr/industrie-services/energie-environnement/021242806475-epr-le-finlandais-tvo-reclame-26-milliards-deuros-a-areva-siemens-1141828.php
http://www.tvo.fi/news/1633




mardi 28 octobre 2014

Nuclear: Areva and Siemens claim now EUR 3.5 billions to the EPR Finnish operator


<script>
  (function(i,s,o,g,r,a,m){i['GoogleAnalyticsObject']=r;i[r]=i[r]||function(){
  (i[r].q=i[r].q||[]).push(arguments)},i[r].l=1*new Date();a=s.createElement(o),
  m=s.getElementsByTagName(o)[0];a.async=1;a.src=g;m.parentNode.insertBefore(a,m)
  })(window,document,'script','//www.google-analytics.com/analytics.js','ga');

  ga('create', 'UA-57622142-1', 'auto');
  ga('send', 'pageview');

</script>
Nuclear: Areva and Siemens claim now EUR 3.5 billions to the EPR Finnish operator
LES ECHOS | On October, 27th at 09:42, updated at 09:59




The power station shall be finished only in 2016 by Areva and Siemens and its commissioning will take place only in 2018, thus accounting for a nearly 9-years delay – AFP – Aira Vahaskari

Until now, the consortium composed of the French group and the German company Siemens claimed EUR 2.6 billions as a compensation due for delays faced by works.
That’s a new step in the confrontation happening between the consortium Areva and Siemens, with the power company Teollisuuden Voima (TVO), the power station operator, in the course of the building of Olkiluoto-3, the Finnish nuclear reactor.
Whereas each of the parties charges the other to be responsible of the delays of the construction, in a press release, Areva has announced that “the consortium claims around EUR 3.5 billions following an additional charge of work, perturbations and lengthening of project, due to events which took place during the construction up to June 2011.


Meanwhile TVO increased its indemnification claim
On its side, TVO claims EUR 2.3 billions to the consortium. In fact, the Finnish power producer increased this amount last week (as it accounted for EUR 1.8 billions) as it corresponds to its evaluation of likely costs and losses up to 2018, which is the intended deadline of the reactor commissioning.
The arbitration process may last several years, said the French group. The French-German consortium and the Finnish site operator, Finnish TVO, oppose in the arbitration court of Paris Chamber of International Trade, which has not set a date to take a decision.

A nine-years delay

In early September indeed, Areva announced that the end of the construction was then set in late 2016. From that date, the trials will start before the commissioning due in 2018. If the schedule is respected, Areva, the nuclear giant and Siemens, the industrial, will have nine years of delay in delivering this reactor, build in the Olkiluoto power station, located on the West coast of Finland.
Areva charges its customer for having delayed the construction because of excessively constraining procedures and of controls deemed far too slow. In its books, the group has thus recorded EUR 3.9 billions of provisions linked to the project, whereas the sale of the reactor amounted for EUR 3 billions.
On its side, in a press release published in the end of the week, TVO estimated that “the contractor is responsible of the delay and of the costs deriving from such delay”. 

Image virtuelle du réacteur nucléaire EPR
(Crédits : Image & Process, AREVA NP)