Nuclear maintenance:
Areva and EDF face unexpected costs
Both groups must comply to a new ASN complex
regulation (ASN: Nuclear Safety Agency) The
restart of a reactor in Le Blayais nuclear plant shall face a delay of several
months.
In Le Blayais nuclear plant, located along the Gironde mouth, the reactor number 3 was stopped in late July 2014, during its third decennial visit; this
stop corresponds to a lengthy maintenance aiming at extending its lifespan for
ten additional years. This reactor of
MW900 should have been restarted in early 2015, fitted with three new steam
generators.
More than a month later, the steam generators are still stored in a
warehouse, waiting for their conformity statement. What for? the nuclear equipment must
comply to the new regulation about pressurized nuclear equipment (such as
tanks, steam generators, among others), which compels the operator to produce
more justifications and safety exercises. “Areva
has not brought all the safety justifications required for their mounting and
their commissioning”, says the Nuclear Safety Agency (ASN, French acronym).
Map of French nuclear power plants with reactors capacities |
A €1 million loss per every production day
Thus, EDF does not expect this reactor to be started before next summer. This delay generates huge over-costs for a project which was first
assessed at €112 million. EDF, the
manager of the operation risk, assesses that the loss faced for each missed day
of production corresponds to €1 million – which would amount to €180 million
for a six months’ time. On its side,
Areva will be charged for the badly budgeted cost corresponding to the
conformity updating and to the complete standstill of its equipment and staff.
But this problem does not affect Le Blayais nuclear plant only: mid-November, EDF put these new regulations forward to justify the
postponement of the commissioning of Flamanville EPR (in Manche). “ This regulation allows the detecting of defaults
on the lid tank of Flamanville EPR at the level of the adapters weldings. This fact has consequences, as the tank lid is not yet ready”, explains Rémy Catteau, manager of ASN
pressurized nuclear equipment.
Even if nobody questions the pertinence of the new regulation,
implementing it may have significant consequences on all chains of the sector,
as the “lengthy refit” is about to start soon. This programme of heavy maintenance affecting EDF nuclear
infrastructures shall begin officially in April, with the third decennial visit
of the first MW1,300 reactor, namely Paluel 2.
The impact of the new regulation shall be heavier than expected, as the
steam generators or the equipment of Flamanville EPR have escaped from the
implementation of the new safety rules, because of a scheduled transitory
period. It won’t be the same for all the
equipment in course of production dedicated to the maintenance of the MW1,300
reactors. EDF has been yet compelled to find
a way to escape this new set of regulations in Paluel 2, by shifting some works
at the end of the scheduled stop.
Going further...
http://www.areva.com/EN/operations-1676/maintenance-and-repair-services-for-nuclear-power-plants.html
https://nuclearstreet.com/nuclear-power-plants/b/default.aspx
Going further...
http://www.areva.com/EN/operations-1676/maintenance-and-repair-services-for-nuclear-power-plants.html
https://nuclearstreet.com/nuclear-power-plants/b/default.aspx
Aucun commentaire:
Enregistrer un commentaire